Our customers save an average of £34,000 on their projects *
Let us handle your Utilities Planning and Applications and see how much we can save you
Start now
Managed Domestic Electricity Planning & Applications
Planning. To save you money
Domestic Mains Electricity Planning, Applications & Management
Whether you need an EV Charging Point, a new Mains Electricity connection, a Mains Electricity Disconnection, to Increase Electricity Supply, or your Mains Electricity Meter moved, we can Save You Time & Money
A common query is How To Get a Domestic Electricity Connection.
What Do You Need?
- New Domestic Electricity Supply
- Disconnect Domestic Electricity Supply
- Increase Domestic Electricity Supply
- Move Domestic Electricity Meter
- Domestic Electricity Service Alteration
- Home EV Charging Points
How we work...
- You submit any existing plans and requirements (and quotes if you have any)
- We analyze and find cost-saving opportunities
- You receive a FREE report showing any potential savings or a fair cost estimate
- Pay a fixed cost for us to Manage your required Utilities Applications
Need Help On A Domestic Electricity Project?
Get In Touch
To speak with a Utilities Planning expert, call us on 0303 040 1213 Mon-Fri 09:00-17:00
We believe in saving you money while creating a relaxing customer journey.
Business With Integrity
Or Let Us Call You
One of our Utilities Planning experts will call you (Mon-Fri 09:00-17:00)
Your number will be used solely to contact you about this enquiry.
Real Results from Past Projects
Case Study: Electricity New 3 Phase Connection 2024
Client: Electrical Engineering Contractor
Project Value: £300,000
Year: 2024
Challenge:
- High-value quotation for a new 3-phase connection
- Design costs deemed unsatisfactory
Solution:
- Conducted a thorough review of design costs
- Engaged in discussions with the supplier and customer
- Agreed an acceptable load within the local network's capacity
Outcome:
- Achieved a significant cost saving of approximately £290,000
Case Study: New Water & Electricity Connection 2024
Client: Master Builder
Project Value: N/A (Review of multiple quotes)
Year: 2024
Challenge:
- Multiple quotes from various providers for water and electricity connections
- Project required road crossings for both services
Solution:
- Identified an opportunity for collaboration on traffic management and road crossings
- Coordinated both providers to reduce the need for multiple crossings
- Minimized excessive traffic management costs
Outcome:
- Achieved a total saving of £5,366 for the customer
Case Study: New Gas Connection 2023
Client: High-Value Domestic Property Developer
Project Value: N/A (Multiple utility connections)
Year: 2023
Challenge:
- Procurement of certified contractor
- Design required both gas and foul water connections to cross at the same point
Solution:
- Identified an opportunity for collaboration on traffic management and road crossings
- Coordinated both providers to reduce the need for multiple crossings
- Minimized excessive traffic management costs
Outcome:
- Achieved a total saving of approximately £3,000 for the customer
Case Study: Phone Line Connections for High-Value Domestic Properties 2023
Client: High-Value Domestic Property Developer
Project Value: £8,000 (Initial Quote)
Year: 2023
Challenge:
- Telecoms provider initially quoted £8,000 for four new phone line connections
- Design costs were deemed unsatisfactory
Solution:
- Conducted a thorough review of design costs
- Challenged the supplier regarding the costs
- Engaged in discussions with Telecoms provider
Outcome:
- Telecoms provider agreed to deliver the work free of charge
- Achieved a total saving of £8,000 for our customer
Case Study: Foul Water Installation 2023
Client: High-Value Domestic Property Developer
Project Value: £10,000 to £15,000 (Potential Savings)
Year: 2023
Challenge:
- Initial structural engineering design included an electric pumping station and sump
- These elements were deemed potentially unnecessary
Solution:
- Procured a certified contractor for the works
- Reviewed the structural design with our subcontractor
- Determined that the system could be gravity-fed, eliminating the need for the electric pumping station and sump
Outcome:
- Achieved a potential saving of £10,000 to £15,000 for our customer
Domestic Electricity supplies are generally single phase 100A services with a max supply of 23kVA and up to 4 Plots and/or a 69kVA 100A 3 phase service without a mains extension.